Monday, August 19, 2013

Siding, Skylights and some Down Time

Staging for the Siding!
 
 
Future Home of a Skylight
 
A Relaxing View
 
The siding company was onsite on Saturday setting up the staging so they can start the siding work this week. It’s a bit nerve wracking as the color is picked out (Maibec White Cedar Shakes with Misty Gray Weathering Oil) and the shingles have been delivered. Now comes the big drum roll. Will it look good? I’m sure it will as we’ve done our homework and it better. My better half reminded me this weekend that it was my deal as I picked it out. So I know it will look good. It will be great to see the siding going up as it will add to the character of the house.
 
We decided to do a change order (I’ll blog about those along the way) and have a skylight put in over the stairs leading to the room over the garage. We had toyed around with the idea of adding a small window on the landing but felt that a skylight would bring in a lot more light. The light will bring with it the added feature of making the stairway feel more open.
 
We spent Saturday afternoon at a friend’s house on the water overlooking the entrance to New Bedford harbor. They had nice gathering of a large group of old friends where we could set aside the frenetic pace of house building, paver and plant moving (another story) and other things that we call life. It was so nice to see everyone and have some down time. And listen to the waves gently shsssh against the shoreline. It was decompressing. And we enjoyed every moment.
 
Enjoy your week.
 

Thursday, August 15, 2013

Doors, Stairs and a Filled in Trench

Kitchen Door that will Lead in from the Porch
 
 
Future Home of the Kitchen Door (and Porch)


Garage Back Door
 
 
Future Home of the Garage Back Door


Stairs Leading Up From the Basement

 
Stairs Leading Down from the Kitchen to the Basement and Garage


Stairs Leading up From the Garage to the Kitchen
 
 
And the Trench is Filled In!
 
 
The doors have all now arrived. Well except for the garage doors which will come somewhere down the road. We now have the kitchen door and the door to the back of the garage sitting in the garage patiently waiting for someone to come along and install them.

The stairs leading from the garage up to the kitchen and down to the basement have finally been added. I’m not sure why they were saved to almost last, but at least they are in. I’m guessing given that the doors are about to be installed and nailed shut (no hardware yet), they needed some way to get into the house.

And the electrical conduit trench has been filled in. Apparently, it had to wait on the inspection. And of course, with an open trench the siding couldn’t be done because I’m guessing they could fall in the trench or something like that. Either way the siding staples are in (yes, they use staples which hold the shingles better) so we don’t have to worry about for want of a nail.

Tomorrow the framers have some cats and dogs to wrap up including the installation of a couple of skylights. Then it’s on to the electrical and siding next week. We hope.

And I still have a bunch of pavers to pick up. My back is saying “yay!”

Not really.

Enjoy your weekend



Monday, August 12, 2013

Electrical, Water & Pavers Update

Electrical Conduit Running to the Telephone Pole
 

The Conduit will be Run Up to the Meter

View from the Pole to the House

Conduit will be Run up the Pole



The Red Tape, which will be buried, will let
Anyone Know that there is an Electrical Line Buried Below.
 
Electrical Circuit Breaker Panel
It's interesting how they ran the Sewer Line Behind it
 
 
The Blue Line is the Water Service Coming Into the House
 
Water Service Curb Stop (Shutoff) Buried about 6 inches Below Grade
 
Pavers - 2 Pallets Moved with Another Started
 
The trenches have dug for the electrical and the water service and the conduit for the electrical, cable and phone has been run. The electrical panel has been added in the basement. Now we’re just waiting on the conduit inspection so that the trench can be filled in. Hopefully that will happen tomorrow as today was a state holiday in RI.  Yup, it was Victory Day today which was formally known as Victory Over Japan Day.  I can even remember as a kid when we had Victory in Europe Day. Both of which celebrated the end of World War II in Europe and Japan. I'm sure like the aging Veteran's that fought in that war, these holidays will pass in time as well.
 
So besides being closer to having power in the house, the water line has also been roughed in so hopefully we’ll have water soon. Not that we can run it anywhere without faucets, but it would be nice to know we’re that close to having it.
 
And we’re making headway on the pavers. I have to stack them out of the way because of the top soil that has to be brought in so I’ll be moving them again somewhere down the road when we start the patio work. I like to think of it as good exercise. My back and knees likes to think otherwise.
 
Enjoy your week.


Sunday, August 11, 2013

I must be Crazy

Future Patio (about 25 x 20) Outlined by 2 x 4's
Green area with Garden and Grass to the right
 
The Stairs from the Deck will come down alongside the Garage wall
We'll tie that into the Patio with a walkway
 

Paver Pile

From the Other End
 
There a lot of things that get thrown at you when building a house.  Change orders that mean we need to give the builder more money or things that looked good on the plans but not in real life (or missed altogether) will all drive you crazy. And then there are those things that are self-induced that you know full well that somewhere along the way you're going to say "I must be crazy!"
 
Mine, at the moment, is self-induced. I saw this ad on Craigslist for pavers. You know, the kind that are used in walkways and patios. I’m planning on building our own patio and when I saw that someone had a boat load of them for sale, I jumped. I’m always on a quest for a “deal”. The ones I found were from folks that had replaced the pavers that served as a patio around the perimeter of their pool with stamped concrete. About 1,000 square feet and perfect for us. One small catch though. They are piled up behind the pool and the pile is about 20 feet long, 10 feet wide and about 5 feet high. And it’s not a neat pile. Just a pile. And they had to be moved from out of the woods behind the pool to the driveway out front (there is no trailer access to the “pile”).
 
When I first saw them, the first word that came to mind was “daunting”. The second thought was OK, so you’ve spent an evening in the emergency room and another morning in an outpatient clinic because of throwing out your back so this is a good idea why? So of course, being the knucklehead that I can be, I bought them anyways.
 
I tried some horse trading early on to try get some help in moving them saying in my best Tom Sawyeresque voice “Don’t you want a patio? I’ll trade a pallet for your help.” No takers (yet).
 
So I started moving them myself yesterday with my trailer. I figure if I do small loads, and listen to my back when it’s murmuring, not screaming to stop, I should be OK. Besides, I have some leftover meds from that ER visit that I kept around for the next back “emergency”.
 
I’ll keep you posted. Now let’s see, where are those meds…?
 
 


Tuesday, August 6, 2013

Big Week Coming Up

The White Cedar Shingles Have Arrived!
 
Stacked in the Garage Too
 

Maibec Nantucket White Cedar Shakes

 
Electric Meter Location
You can see the Telephone Pole in the Background where the Trench will go


View Looking from the Pole Towards the House
The Orange Lines Mark out the Utilities Trench
 
The Shingles are in! A couple of loads and a side order of shingles have arrived. We went with the Maibec White Cedar R & R’s (rebutted, resquared) shingles for our siding. They’ve been coated with a gray weathering oil to give it that Cape Cod look. We think the color will look excellent with the white trim. Rebutted, resquared means that the bottoms of the shingles have been squared off. This provides a more even shingle and helps the work move faster. They’re pricier but overall, it will be better look.
 
Also the trench for the utilities (electrical, phone & cable) has been marked out. Our plan is to bury the lines as the closest pole is out front and we didn’t want any wires coming into the front of the house.  Again, it’s pricey but overall it will give the house a nice neat look without any wires hanging from it.
 
At the same time that the electrical trench is going in we are having the trench dug for the water service. The curb stop is already in from the last house so it should be pretty straight forward. Of course, it’s required that the installer be licensed with the local water authority to do the install so this narrows the playing field down a bit. The company we have hired does a lot of work for our builder so we know we have the right person for the job.
 
So if everything goes according to my plan (I suppose I should check with the builder…) by the end of the week, we’ll have electrical service and water service installed. And maybe the siding started.
 
The house is slowly but steadily coming alive.

Monday, August 5, 2013

The Perfect Weekend

Charlestown, RI Seafood Festival
With all kinds of Seafood
 
Rides - Puke-A-Rama
 
More Food
 
Clam Cakes & Lobstah Rolls
 
 
Newport, RI
Concert Night on the Wharf
 
Double Decker Food Bus
 
Still a Working Waterfront
 
With time to Relax
 
Robin Wilson (center) Lead Singer for the Gin Blossoms in the Crowd
 
Like bookends, our weekend was spent doing yard work and stuff in the middle framed by some down time enjoying life. We spent the day on Friday at the Charlestown, RI Seafood Festival where we enjoyed  a couple of lobster rolls and an order of clam cakes. The clam cakes were disappointing as they had very few, if any, clams. The lobster rolls did not disappoint and made up for their seafood cousins. The weather (or “weatha” in our Boston accent) was perfect. It looked like a fun place to bring the kids as there were the usual carnival type rides and a bunch of games to play.
 
Saturday and Sunday were spent catching up on yard work. Our crab grass weeds at the house being constructed are doing tremendous and are a deep shade of green. I even broke the weed whacker out of the box where it has been aging for the past three weeks. It’s a noisy bugger though. Maybe when this one goes I’ll opt for one of those quieter battery powered ones.
 
Sunday night we were in Newport where we went to a 90’s tour concert where Fastball, Gin Blossoms, Sugar Ray and Smash Mouth all played. It was a lot of fun with Sugar Ray and Gin Blossoms really getting the crowd going. We missed Fastball as we outside sitting on the dock having dinner when they came on. Smash Mouth must have been having an off night and we left about half way into their set like a couple of old fogies.
 
It was wide age ranging crowd. This was music from when my children were growing up and there were a lot of parents with their kids there. The best picture that I missed was of a boy who was about 11 sitting in his seat eating ice cream with earplugs in while his parents danced to the music. It’s funny while we’re becoming our parents, our kids are becoming us. The picture I did get (and nobody else but she will see) was of a lady that we know from church dancing on the chairs. Not something you would normally see in church. And she made us promise not to tell anyone. I’m pretty sure she’s not going to remember a lot anyways.
 
We had a great time and really enjoyed the show. And our ears have even stopped ringing. It was a perfect way to start and end a weekend with some good work done in between.
 
The way life should be all of the time.
 
Enjoy your week.
 

Friday, August 2, 2013

Trim Work

Finishing the Garage Door Trim
 
Rubber Tape over Edge of Windows Before Trim Work
This Helps to Seal the Windows from Water 


Trim Work. Wood Filler & Paint will Neaten It Up
 
Soffit with Soffit Vent
 
Soffit Vent
 
Windows & Corners Trimmed Out
 
We're Ready for the White Cedar Shingle Siding
 
 
The trim work is pretty much done with the windows all trimmed off and the corner boards in place. The garage doors are all also trimmed off.
 
The soffits with their trim are well along the way. It was interesting that they now use plastic vents as soffit vents.  I’ve seen all kinds of soffit vents. 3” round ones, 6” rectangle ones and metal ones that go in front of the gutter and so on.
 
 
These vents work in conjunction with the ridge vents on the roof peak where heated air moves by convection drawing the cooler air in at the soffits and venting the hotter air through the ridge vent. This helps to keep the roof cooler extending the life of the roof. It can also help keep moisture out of the attic which can create a mold problem.
 
The vents and roof rafters need to be kept clear so that the air can move through. Too often folks paint the vents thus clogging them or they block the vents or rafters with insulation. Doing any of that defeats their purpose and you’ll be replacing your roof in no time or hiring a mold remediator.
 
Now that the trim work is up, it won’t be long before the siding starts going on the house. It will be fantastic to have the outside completed. We’re almost four months into construction and a year and a half into the planning.
 
And it’s all coming together.